A Landmark Investment in Kansas City's Tech Future
Kansas City's role as a national AI hub was solidified Tuesday as Patmos Hosting Inc. announced it has secured a monumental $100 million C-PACE loan. The financing, provided by PACE Loan Group, is the largest of its kind in Missouri history and will fund the completion of Patmos's ambitious AI Campus in the former Kansas City Star building at 1601 McGee Street.
This investment marks a pivotal moment for the city's tech infrastructure, transforming a historic Crossroads landmark into a cutting-edge 35-megawatt data center designed for high-density AI and high-performance computing workloads. The deal makes the Patmos facility the first assessed clean energy data center in history, setting a new standard for sustainable technology development in the region. Since beginning construction in late 2024, Patmos has already signed two publicly traded tenants to multi-year leases, validating the project's rapid progress and market demand.
From Printing Press to AI Powerhouse
The iconic green glass building, once home to The Kansas City Star's printing operations and briefly considered for a new Royals stadium, is now the headquarters for Patmos and the heart of its people-centric AI mission. Beyond the data halls, the 421,112-square-foot campus will feature nearly 150,000 square feet of multi-tenant technology hub space, including co-working and event areas.
Joe Morgan, Chief Operations Officer for Patmos, emphasized the project's broader vision for the city. "We are pretty far along on building out the AI campus and turning the building into a tech hub for Kansas City with co-working and event spaces," Morgan told The Kansas City Star. "This is going to allow us to finish that plan and that mission that we’re on." The adaptive reuse of the building accelerates speed-to-market and establishes a significant tech anchor in the vibrant Crossroads Arts District.
Financing a Sustainable Future
The record-breaking $100 million loan is a Commercial Property Assessed Clean Energy (C-PACE) financing package. This specialized program, managed by Show Me PACE in Missouri, provides funding for energy-efficient infrastructure improvements. The loan is repaid over time through an assessment on the property's tax bill. For Patmos, these funds are specifically earmarked for optimizing HVAC systems, plumbing, and other equipment essential for managing the immense cooling and electrical loads of an AI data center.
"C-PACE made a lot of sense for this renovation. Many of the conversion costs were eligible, and the long-duration capital is well aligned with Patmos’s business plan," said Rafi Golberstein, CEO and founder of PACE Loan Group. The project pioneers the use of C-PACE for data centers, a model that could be replicated nationwide. According to a report from Data Center Knowledge, Patmos will leverage a closed-loop water system and collaborate with a local chilled water company, which could reduce the energy used for cooling by nearly 100%.
A Different Approach to Data
While hyperscale giants like Google and Meta build massive new data centers in Kansas City's Northland, Patmos is carving a different path. The company is intentionally focusing on the mid-market, targeting enterprise customers and small-to-medium-sized businesses (SMBs) that are often priced out by larger providers.
"We’re not trying to make a deal with any of the hyperscalers," COO Joe Morgan explained to Data Center Knowledge. "Part of our strategy is to create smaller colocation spaces to make sure that SMBs that want to be able to get into AI have the ability to do so – basically guaranteeing small businesses have the ability to be successful and compete at the same level." This strategy positions the Patmos AI Campus not just as infrastructure, but as a democratizing force for AI access within the Kansas City business community.
| Attribute | Patmos AI Campus (Crossroads) | Hyperscale Data Centers (Northland) |
|---|---|---|
| Location Strategy | Urban Retrofit (Adaptive Reuse) | Suburban Greenfield (New Construction) |
| Target Scale | 35 MW (Mid-Market) | Gigawatt-Scale (Over 1,000 MW) |
| Primary Customer | Enterprises & Small/Medium Businesses | Big Tech (Meta, Google, AWS) |
| Community Model | Integrated Tech Hub with Co-working | Dedicated, Secure Compound |
| Financing Highlight | Sustainable C-PACE Loan | Corporate Capital & Tax Incentives |
What's Next: Completion and Regulation
With financing secured, the final phases of construction are underway. The project is scheduled for completion and to be fully operational by the end of 2026. This includes the buildout of the remaining data center capacity and the commercial office and event spaces.
Meanwhile, the rapid growth of data centers in Kansas City has caught the attention of city officials. The Kansas City Council is expected to consider changes to zoning codes that could add more restrictions and review processes for future data center developments, particularly concerning utility service adequacy. While Patmos has focused on the efficiency of retrofitting an existing building, the broader conversation around the environmental and energy impact of data centers is set to continue in Kansas City.
What is a C-PACE loan?
C-PACE (Commercial Property Assessed Clean Energy) is a financing mechanism that allows property owners to fund energy efficiency, renewable energy, and resiliency projects. The loan is repaid over time through a special assessment added to the property's tax bill, providing long-term, fixed-rate financing.
Why is this $100 million loan significant for Missouri?
This is the largest C-PACE loan in Missouri's history, according to the Show Me PACE program. It also marks a pioneering use of this green financing tool for a data center project, which could serve as a model for future sustainable tech developments in the state and nation.
What was the former Kansas City Star building used for?
The building at 1601 McGee Street was the printing press and distribution facility for The Kansas City Star newspaper until it was closed in 2019. The site was also once a leading contender for the location of a new downtown ballpark for the Kansas City Royals.
What makes this data center energy-efficient?
The C-PACE loan will fund significant upgrades to the HVAC and cooling systems. Patmos plans to use a closed-loop water system and partner with a local chilled water company, which drastically reduces the massive energy consumption typically required for cooling AI-grade servers. Retrofitting an existing building is also inherently more sustainable than new construction.
Sources
- Patmos secures $100 Million C-PACE loan to complete AI data center in Kansas City 2026-01-12
- Data company buys former Star building in Crossroads for AI campus 2026-01-12
- Patmos secures record $100M PACE loan for Kansas City Star building project 2026-01-12
- Patmos Scores $100M Clean Energy Loan for Kansas City Data Center 2026-01-12
- A Kansas City data center is one of the first in the nation to get a clean energy loan 2026-01-15